Rehabilitation Paused for Flint Park Fields
Larchmont village officials were very excited about the rehabilitation of the Flint Park fields A and B and had hoped to have them up and running in time for the fall season. The initial project aimed to improve the condition, drainage, durability, and playability of the fields through a reinforced natural turf system and an updated stormwater collection system which would connect to the existing municipal drainage system. Unfortunately, an unexpected historic discovery has halted the project.
Prior to construction, environmental testing was done which included soil sampling at 18 locations. The testing found conditions consistent with urban fill commonly found in developed areas but did not identify waste indicators. Municipal solid waste was not encountered at any of the original sampling locations. The site is also not listed in New York State Department of Environmental Conservation’s (NYSDEC) database of active or inactive landfills. Regardless, the Village decided to proactively remove all of the top layer of dirt, properly dispose of it, and replace it with new dirt (also called certified clean root-zone material) improving the safety of our longstanding recreational fields.
Nonetheless, on August 19, material believed to be municipal solid waste was uncovered in one localized area during the installation of a stormwater manhole. NYSDEC arrived at the site that same day, before the Village had an opportunity to evaluate or test the newly uncovered material, and work was halted. This isolated area was the only location where such material was encountered during construction.
The site remains fenced and locked, and the soils in question have been covered to minimize exposure. The issues have been contained. The rest of Flint Park remains safe and enjoyable for residents and visitors alike.
The Village’s consultant continues to monitor the erosion and sediment control measures and notify the contractor of any required repairs.
The material has been stockpiled and covered and will undergo environmental testing to determine the appropriate disposal process. Additional test pits are also proposed to evaluate the area before the stormwater connection is completed. The Village and its consultants have provided NYSDEC with updated technical information and are working cooperatively with the agency as it reviews the proposed measures and next steps. The project will resume once that guidance is in place.